Installation of LMP in Murmansk.

Customer: Halliburton in support of KarMorNeftegaz (JV Exxon Mobil  &  Rosneft), Murmansk, Barents Sea coast.

The construction of LMP for the preparation of drilling muds in the city of Murmansk was an integral part of activities for exploratory drilling in the Kara Sea. Successful implementation of the project allowed the preparation and dispatch of drilling fluids, as well as bulk materials, necessary for the drilling of the Universitetskaya-1 well in August-September 2014, within the time-frame.

Scope of Work: Supply of materials, installation of equipment and process pipelines, construction of prefabricated industrial buildings with a total production area of ​​1 000 m2, hydrotesting of pipelines, commissioning.

Capacity of the tank farm is 12 000 bbl.

In this project, RIKS PCS acted as a general contractor for the execution of construction and installation works and a supplier of materials and equipment.

The project has been fulfilled on schedule and put into operation.

In 2015 RIKS PCS demobilized all the equipment of LMP in Murmansk and shipped to another location.